Solar Lattice

Function

Export limitation

ID
func:export-limitation
IRI
https://solarlattice.org/kb/func/export-limitation
Status
active
Also known as
export limit, feed-in limitation, export control, active power feed-in limitation at PCC, power export limit, PEL, Export Limiting, Export Power Control, Export limitation control
Category
Control
Function kind
control

Export limitation caps the active power that the generators feed into the grid at the point of connection. Network operators often impose such a cap to meet grid code requirements. A meter at the grid connection measures export. When available PV power is greater than the site load, the inverter reduces its output and the excess power is lost. A sudden change in load can still cause brief overshoot above the limit, but the control limits how long it lasts. Fail-safe fallback settings keep export within the limit when parts of the system fail. On SMA CORE2 and Sunny Tripower X, you configure the meter channels and then set the active power to closed loop control with manual signal source. The active power setpoint is a percentage of total system power, where 0% gives zero export. Setting time and active power gradient adjust how fast the limit is reached. Enphase IQ8 Commercial systems set the power export limit through the grid profile. The settings are a watt threshold, enable or disable, per-phase or aggregate limit, export response time, and communication loss time. If export stays above the limit for longer than the response time, the Enphase gateway ramps PV down to zero. On Generac PWRcell inverters, an Export Limit of 0 works as zero export. Export Limiting can be set only once and the value can only be decreased. If the inverter loses communication with its CTs, it ramps its output down until export stops. Solis S6 hybrids can enable export power control with or without a battery, using the energy meter supplied with the inverter. Fronius Datamanager, SMA Sunny Tripower Smart Energy and FIMER inverters with a meter also provide this function.

<!-- review notes

Parts

Claims

requires

c1 drafted · lead SMA Data Manager M

Scope: products Sunny Tripower CORE2

The Data Manager (EDMM-10) is the master device, and the CORE2 inverter is added under it.

c2 drafted · lead SMA Energy Meter

Scope: products Sunny Tripower CORE2, Sunny Tripower X (international)

EM-20 is the example meter. For CORE2 the article says other meters can also be used.

review note: support check: partial - CORE2 article lists the EM-20 as needed and says other meters can be used; STP X article only uses EM-20 as illustration and doesn't say it's required.

c3 verified · fact Installer

Scope: products Generac PWRcell Inverter (X7602, XVT076A03, XVT114G03)

A qualified installer sets the Export Limit value.

verified by: review-workflowverified on: 2026-10-24

c4 drafted · lead Consumption metering proposed

Consumption CTs or an external meter at the service measure import and export.

review note: support check: partial - Enphase uses Consumption CTs and Solis uses a meter with CTs measuring consumed and imported power, but the passages don't say they measure export or that consumption metering is required generally.; review: partial - Enphase checks export against its Consumption CT readings and Solis curtails based on its meter's CT data, but the Solis meter is described as measuring consumed and imported power (not export), and neither passage says metering is required in general.

c5 drafted · lead Enphase IQ Gateway

Scope: products Enphase IQ8 Commercial Microinverters proposed

IQ Gateway Commercial 2 uses production and consumption CTs to limit PV output.

setting_range

c6 drafted · lead ≥ 10 SEC

Scope: products Enphase IQ8 Commercial Microinverters proposed

Conditions: Communication loss time limit setting of the Enphase power export limit on IQ Gateway Commercial 2