Solar Lattice

Fault codes › CPS › CPS SCA100K-T-US-480 / SCA50K-T-US-208

CPS SCA50-100K-T Protect0030

Code
Protect0030
Shown as
Bus Soft start time out
Vendor severity
Protection
Page
130
ID
fc:chint-sca-50-100k-t-protect30
IRI
https://solarlattice.org/kb/fc/chint-sca-50-100k-t-protect30
Status
active
Also known as
Protect0030, protect30, CPS Protect0030, Bus Soft start time out
Category
Inverters
Class fault drafted · lead
Production stops drafted · lead
Clears after a manual reset drafted · lead

Decoded

Reports inverter overcurrent; look at inverter; do: inverter restart, inverter replacement.

What can be behind Inverter overcurrent

Failure modes that present as the reported condition, and the tests that tell them apart.

Defined in

The manufacturer's own cause and corrective text is not reproduced here.

Same condition on other equipment

CPS
CPS SCA25KTL-208 Protect0030, CPS SCA25KTL-480 Protect0030, CPS SCA50-100K-T PFault0080, CPS SCA50-100K-T Protect1060, CPS SCA50-100K-T Protect0240, CPS SCH100-125KTL Protect0030, CPS SCH125KTL-AIO Protect0030, CPS SCH200-250K-T Protect0240, CPS SCH275KTL Protect0030, CPS SCH350KTL Protect0030
Canadian Solar
Canadian Solar 185-255K IGBT-OV-I
KACO new energy
KACO new energy blueplanet TL3 184, KACO new energy blueplanet TL3 185, KACO new energy blueplanet TL3 186, KACO new energy blueplanet TL3 206, KACO new energy blueplanet TL3 97
Schneider Electric
Schneider Electric CL125 022
Solis
Solis 3P-5G-US IGBT-OV-I, Solis RHI-1P-HV IGBT-OV-I, Solis S6-EH1P IGBT-OV-I, Solis S6-EH2P IGBT-OV-I, Solis S6-EH3P30-60K IGBT-OV-I, Solis S6-EH3P75-150K IGBT-OV-I, Solis S6-GC IGBT-OV-I, Solis S6-GU IGBT-OV-I
Yaskawa Solectria
Yaskawa Solectria PVI-25TL-R Protect0030

Same code in other families

Claims

defined_in

c1 drafted · lead CPS SCA100K-T-US-480 SCA50K-T-US-208 User Manual Rev 1.0

has_event_class

c2 drafted · lead Fault (device stops or needs intervention)

from the code prefix

reports

c3 drafted · lead Inverter overcurrent

affects

c4 drafted · lead Inverter

has_production_effect

c5 drafted · lead Trip (production stops)

Power cycle needed to clear implies inverter stopped

review note: support check: partial - Power cycle and replacement are recommended, but a stop of production is not stated; it is only implied.

has_recovery

c6 drafted · lead Manual reset (operator restarts or acknowledges)

AC and DC power cycle; replace inverter if fault persists

mitigated_by

c7 drafted · lead Inverter restart

c8 drafted · lead Inverter replacement

Only if restart does not clear the fault

applies_to

c9 drafted · lead CPS SCA100K-T-US-480 / SCA50K-T-US-208

Data