The SMA Inverter Manager is an SMA device that monitors and controls inverters in decentralized PV plants. It is meant for indoor use only. One unit can handle up to 42 Sunny Tripower 60 or Sunny Highpower 75 inverters, or up to 20 Sunny Tripower Storage 60 units with battery storage. It may only be used with the Sunny Tripower 60, the Sunny Tripower Storage 60 and the Sunny Highpower Peak1. You need the LCS-Tool on a PC connected over Ethernet to commission and maintain the inverters. The LCS-Tool is the main user interface for the plant. The unit has two Ethernet ports: LAN 1 goes to the external network and LAN 2 goes to the inverters. An RS485 port in SunSpec mode connects the optional I/O Box and SunSpec-compatible weather stations. Monitoring works through Sunny Portal or SunSpec Modbus TCP. Active and reactive power setpoints can be a constant value, a curve, or a remote command sent via SunSpec Modbus TCP with the I/O Box. If the inverters lose communication with the Inverter Manager, they switch to a fallback state that was set in advance in the grid code file or through the LCS-Tool. Its operating temperature range is -40 °C to +75 °C, and it runs on a 9 to 36 V DC supply.

Claims

manufactured_by

c1 drafted · lead SMA

review note: support check: partial - The passages name the product 'SMA Inverter Manager' and the text mentions SMA, but nothing explicitly states SMA manufactures it.

instance_of

c2 drafted · lead Monitoring data logger

Device for monitoring and controlling inverters in decentralized PV plants

max_count

c3 drafted · lead ≤ 42 NUM

Conditions: Sunny Tripower 60 or Sunny Highpower 75 inverters monitored and controlled per Inverter Manager

c4 drafted · lead ≤ 20 NUM

Conditions: Sunny Tripower Storage 60 units with battery storage per Inverter Manager

operating_temperature

c5 drafted · lead -40–75 DEG_C

Conditions: Operating temperature range; relative humidity 5 % to 95 % non-condensing

compatible_with

c6 drafted · lead Sunny Tripower 60

Up to 42 units; to be operated exclusively with Sunny Tripower 60, Sunny Tripower Storage 60 and Sunny Highpower Peak1

c7 drafted · lead Sunny Highpower PEAK1

c8 verified · fact Sunny Tripower Storage 60 proposed

Up to 20 units with battery storage systems

verified by: review-workflowverified on: 2026-10-24

requires

c9 drafted · lead SMA LCS-Tool

LCS-Tool on a PC via Ethernet is the primary user interface and is needed to commission and maintain the inverters through the Inverter Manager

c17 drafted · lead SMA Digital I/O Box proposed

Optional; required to receive digital grid management signals

review note: support check: partial - I/O Box is described as optional and receiving grid management signals, but 'requires' is not strictly stated beyond that function.; review: partial - The passages support that the I/O Box receives digital grid-management signals and relays setpoints, but they mark the I/O Box interface as optional ('en option'), so the bare 'requires' relation is not supported.

uses_protocol

c10 drafted · lead Ethernet

LAN 1 to the external network, LAN 2 to the inverters (RJ45); maximum Ethernet cable length 100 m

c11 drafted · lead RS-485

D-Sub 9 RS485 in SunSpec mode for the optional I/O Box and for SunSpec-compatible weather stations; maximum RS485 cable length 1200 m

c12 verified · fact SunSpec Modbus

SunSpec Modbus TCP is used for plant monitoring and for remote active/reactive power setpoints

verified by: review-workflowverified on: 2026-10-24

c13 drafted · lead Modbus TCP

implements

c14 drafted · lead Active power setpoint proposed

As a constant value, a curve, or a remote command via SunSpec Modbus TCP with the I/O Box

c15 drafted · lead Remote dispatch

Grid management commands arrive as digital signals at the I/O Box, which passes setpoints to the Inverter Manager; it then controls every inverter in the plant

c16 drafted · lead Communication-loss fallback

If communication with the Inverter Manager is lost, the inverters switch to a predefined fallback state set in the grid code file or through LCS-Tool; a system fallback toward a superior SCADA or power plant controller can also be configured

certified_to

c18 drafted · lead UL 508 proposed

c19 drafted · lead UL 60950-1 proposed

c20 verified · fact CSA C22.2 No. 60950-1-07 proposed

verified by: review-workflowverified on: 2026-10-24

c21 drafted · lead EN 60950-1 proposed

c22 drafted · lead EN 55022 proposed

Class A

c23 drafted · lead EN 61000-3-2 proposed

Class D

c24 drafted · lead EN 61000-3-3 proposed

c25 drafted · lead EN 55024 proposed

c26 drafted · lead FCC Part 15B proposed

Class A

Referenced by

Data