Grid earthing system incompatibility

ID
fm:earthing-system-incompatibility
IRI
https://solarlattice.org/kb/fm/earthing-system-incompatibility
Status
active
Also known as
TN-C connection, IT grid, IT network not supported, Delta IT utility grid, improper PE connection, TT grid, touch voltage on enclosure, grid configuration, TN-C system, IT not supported, delta IT networks, earthing system compatibility, corner grounded Delta

This failure happens when an inverter is connected to a grid earthing system or grid configuration that the model does not support, such as an IT grid on a model without IT support, or a delta grid other than the one specified. Support depends on the model. Some hybrid models do not support IT networks and are not recommended for TN-C, while some commercial and utility models support all major earthing systems. On a TN-C system with a large load imbalance, a touch voltage can appear on the inverter enclosure. Connecting to an unsupported delta grid can damage the inverter. Before installing, verify the site earthing system and confirm it is compatible with the inverter model, using the manufacturer compatibility table and the installation manual. If TN-C cannot be avoided, keep the unbalanced output function disabled. Where possible, convert the installation to TN-C-S before connecting the inverter. Balance loads across the phases, and do not use a neutral terminal for loads when there is no neutral conductor. For non-standard topologies, contact the manufacturer and the utility. Never change earthing arrangements without approval from the electrical authority or a qualified engineer.

<!-- review notes

Claims

affects

c1 drafted · lead Inverter

Each inverter model supports only certain grid earthing systems or grid configurations; for example some hybrid models do not support IT grids, and TN-C is not recommended for them.

presents_as

c2 drafted · lead Touch voltage on enclosure proposed

On TN-C systems, a large load imbalance can put a touch voltage on the inverter enclosure under some operating conditions.

caused_by

c3 drafted · lead Installation error

Connecting the inverter to a grid topology or earthing system the model does not support. On one product line, delta grids other than the supported one may damage the inverter and void the warranty.

review note: support check: partial - The delta-grid damage and warranty caution is stated, but nothing explicitly names installation error as the cause. Only best practices that imply it are given.

c4 drafted · lead Recurring line-to-ground faults proposed

On a 480 V delta service, co-located loads that cause recurring line-to-ground faults effectively turn it into a corner-grounded delta grid, which exposes the inverters to excessive line-to-ground voltage.

review note: support check: partial - u25 describes recurring line-to-ground faults on 480 V delta giving an effective corner-grounded delta and excessive line-to-ground voltage. It does not say this is an earthing incompatibility, and it prescribes isolating the PV system from the fault source.

mitigated_by

c5 drafted · lead Earthing system verification proposed

Check the site earthing system and confirm it is compatible with the inverter model before installing.

c6 drafted · lead TN-C-S conversion proposed

Where possible, convert a TN-C installation to TN-C-S before connecting the inverter.

c7 drafted · lead Inverter settings review

If a TN-C connection cannot be avoided, the unbalanced output function must stay disabled.

c8 drafted · lead Balanced phase loading proposed

On three-phase systems, balance loads across all phases. If there is no neutral conductor, do not connect loads to a neutral terminal.

c9 drafted · lead Contact manufacturer service

Contact the manufacturer when the site topology or transformer configuration is outside the supported standard configurations.

c10 drafted · lead Utility company consultation

Get the exact connection specifications from the electric utility; local regulations and distribution system operator requirements take priority.

c11 drafted · lead Proper installation

A qualified electrician should do the work, following local regulations and the model-specific installation manual. Earthing arrangements should never be changed without approval.