Protection coordination, also called selectivity or selective coordination, means setting protective devices so that the device closest to a fault clears it and the devices upstream wait. A coordination study takes the device settings, including CT and VT ratios, puts them into a short-circuit model of the system and works out the clearing times for each zone of protection. The results are shown as time-current curves, fuse selectivity ratios or breaker selectivity tables. Some fuse families only need a 2:1 amp-rating ratio between upstream and downstream fuses to be selective. Curves need a time margin between them to allow for timing errors, relay overshoot and CT errors. One relaying seminar gives a typical coordination time of 0.4 s for electromechanical relays and 0.3 s for digital relays. There is a trade-off: keeping upstream breakers selective can make them slow or less sensitive to low arcing currents. Methods such as zone-selective interlocking try to give both fast protection and selectivity. When coordination cannot be complete, the study aims to get as much selectivity as possible while still protecting the equipment. In PV work, a high share of PV on a feeder can change fault current levels, so the utility may need to review existing protection coordination before it approves an interconnection.

<!-- review notes

Claims

related_to

c1 drafted · lead Overcurrent protection

Coordination studies set the types, characteristics, settings and ratings of overcurrent protective devices.

c2 drafted · lead AC circuit breaker proposed

Breaker trip units must be set so that pickup thresholds stay nested from one tier to the next.

c3 drafted · lead AC arc flash

Selectivity can force upstream breakers to be less sensitive to low-magnitude arcing faults.

c4 drafted · lead Single-line diagram

Coordination studies need a one-line diagram, and their reports include one.

c5 drafted · lead Automatic reclosing

Sequence coordination aligns substation breakers with downstream reclosers and fuses.

c6 drafted · lead Distributed energy resource

High PV penetration can change fault current levels, so existing distribution protection coordination needs review.