Solar Lattice

DetectionMethod

Inverter startup commissioning verification

ID
method:startup-commissioning-verification
IRI
https://solarlattice.org/kb/method/startup-commissioning-verification
Status
active
Also known as
commissioning checklist, startup services, power run, pre-commissioning, Pre-Commissioning Checks, Startup and Verification Test, Startup Checklist, Initial verification, Installer Commissioning Checklist

Startup commissioning verification is the set of checks done when an inverter is first started. For safety, technicians follow the manufacturer's commissioning checklist. IEC 62446-1 describes the commissioning tests and inspection criteria used to confirm that a grid-connected PV system is installed safely and works correctly. The same tests can be repeated later as periodic retests. Some inverters must be commissioned through an installation wizard in their internal web interface. When there are several inverters, each one is commissioned separately. Manufacturer startup services need full DC and AC power at the unit. The AC must come from the utility, not from a generator. Where an export meter is used, the key step is checking CT orientation. With all inverters off, measure each phase with a clamp meter and confirm the reading matches the meter's displayed value. One limit: monitoring portals can show invalid data for the first days after commissioning, which skews long-term data. The fix is to delete those days or move the commissioning date in the portal.

<!-- review notes

Claims

produces

c1 verified · fact Meter vs display mismatch

During CT verification, current on each phase is measured with a clamp meter while all inverters are off. The reading is compared with the export power meter value, and the two should match on every phase. A mismatch points to a problem with CT orientation or measurement.

verified by: review-workflowverified on: 2026-10-24review note: support check: partial - Procedure (inverters off, clamp meter per phase, compare with EPM, readings match) is stated, but the passage doesn't say a mismatch points to CT orientation/measurement problems, though that is implied by the step's purpose.

Referenced by

Data