Locus Energy offers an automated incentive reporting service. It validates and submits SREC generation data for 11 incentive programs across the country and also answers questions about SRECs. Interval data from the revenue-grade production meter is combined into a monthly submission. The program checks the data and then issues SRECs to the account holder. To enroll, register the system with the program, such as Mass CEC PTS or PJM GATS. Name Locus Energy as System Representative or Third Party Reporter, then email the completed reporting setup form to the Locus reporting team. For Massachusetts you also send the Automated Incentive Reporting Contract. The setup form asks for system IDs, the LGate comm device ID, the date in service and installer contact details. Setup forms must arrive by the last business day of the month to be reported for that month. If a form is late, no SRECs are lost, because the next report covers both periods. The LGate stores about two months of data. If it stays offline longer than that, send the reporting team a recent inverter or backup meter reading so the missing generation can be accounted for. Contracts run for five or 10 years and can be renewed, depending on the program.
Claims
issued_by
c1 drafted · lead
Locus Energy proposed
Locus Energy runs an automated incentive reporting team that validates and submits generation data to the programs.
applies_to
c2 drafted · lead
Locus Energy LGate gateway proposed
The LGate production meter records generation at 5 minute intervals and holds about two months of data in internal memory.
c3 drafted · lead
United States proposed
Covers 11 incentive programs nationwide, including Mass CEC/PTS, PJM/GATS, NEPOOL, WREGIS, the CSI utilities and MRETS.
c4 verified · fact
Massachusetts proposed
Reporting to the Massachusetts CEC PTS program; Locus must be designated as System Representative.
verified by: review-workflowverified on: 2026-10-24
c5 drafted · lead
PJM market area proposed
Reporting to GATS PJM-EIS; Locus must be designated as Third Party Reporter.
warranty_term
c6 drafted · lead
nominal 10 YR
Conditions: Longer of the two incentive reporting subscription contract options; renewal depends on the program and its enrollment rules
review note: review: partial - The passage supports a 10-year contract as the longer of two subscription options, renewable depending on the program and its enrollment rules, but it describes a service subscription contract, not a warranty term, so the 'warranty term' relation is not…